Toggle menu

Temporary traffic signals consultation guidance

Works promoters must determine traffic management requirements based on their own risk assessments. However, we can intervene under statutory powers. We will expect all applicants to show they have considered potential impacts before seeking approval for temporary traffic signals.

Below are examples, not an exhaustive list; this tool is a guide, not a list of hard and fast rules. Impacts might include:

  • road users disrupted (including pedestrians, cyclists and public transport users and operators)
  • accessibility at public buildings (such as health centres, hospitals, schools, children's centres, council or government offices, or at fire, police or ambulance stations)
  • economic impacts (including the impact on freight, business and the local economy in general)
  • other utilities' works already taking place or planned for the same dates (or within two working days)
  • statutory or regulatory obligations (for example; Equality Act 2010, Traffic Management 2004)
  • impacts on planned events in or around Gateshead (for example; Great North Run or a home premiership football match)

 

 Short duration
up to two days or a weekend

Medium duration 
up to 14 days

Long duration
any greater duration

Low impact 

For example:

  • Little impact on any road users
  • No diversions
  • Only minor delays expected.
  • Not a scheduled bus route
  • No bus stops taken out of use
  • No impact on public buildings
Consultation not required Consultation not required Consultation not required

Moderate impact

For example:

  • Some delays and/or diversions
  • Buses affected/stops suspended
  • Some impacts at public buildings
  • Some adverse economic impact (for example; delays on major freight routes)
  • Might affect adjacent strategic route
Consultation not required Consultation needed Consultation needed

High impact

For example:

  • the road is a strategic route
  • significant diversions or delays likely
  • significant impacts at public buildings
  • significant traffic impacts
  • permanent traffic signals affected
  • planned event affected
Consultation needed Significant consultation needed Significant consultation needed

Key

Green  Consultation will not normally be required, other than with those directly affected. The emergency services are unlikely to be interested unless directly affected.

Amber  Consultation will be needed, including police. A minimum of seven working days must be allowed for consultees to respond; valid points raised must be fairly addressed.

Red Significant consultation needed, including police. A minimum of 12 working days must be allowed for consultees to respond; valid points raised must be fairly addressed. Shorter notice periods will not usually be considered. 

This is a guide, there will always be non-standard situations which require a different approach. Where consultation is required, it must be meaningful. Only organisations likely to be affected will normally need to be consulted. The organisations which most commonly need to be consulted in relation to work in Gateshead are shown on our application form. The works promoter is responsible for consulting them.

To ensure compliance, the our Traffic Planning section will liaise with the emergency services when it is necessary. Although it will still be for the works promoter or their agents to respond to any issues they raise and to comply with any requirements they may reasonably impose. Enough time must be allowed for this, and it should be borne in mind that the officers concerned, especially at the police, may work shifts.