Validation requirements
Part 3, Class R (Agricultural building to a flexible commercial use B8, C1, Class E)
Considerations:
- Transport and highways impacts of the development
- Noise impacts of the development
- Contamination risks on the site
- Flooding risks in relation on the site
Refer to Part 3, Class R and Paragraph W of the GPDO 2015
Schedule 2 of the Town and Country Planning General Permitted Development Order 2015 (as amended) (opens new window)
Document requirements:
- Plan indicating the site and showing the proposed development.
- Flood Risk Assessment where in Flood Zone 2 or 3 and Flood Zone 1 (in critical drainage area)